Skip To Content

Projects Status

Updated June 7, 2018

City of Farmington Hills 2018 Major Road Projects

Map of City of Farmington Hills Major Road Projects
 
Construction Mailing List Email Icon
Join the Construction Mailing List.  You will receive periodic updates via email.
 
Michigan Department of Transportation (MDOT) 2018 Road Repair Projects
Click here for Project Dates
Capital Improvement Projects-2018, Interactive Map
Capital Improvement Projects - 2018
 

Interactive Map

13 Mile Road Rehabilitation, Middlebelt Road to Inkster Road

13 Mile Road between Middlebelt and Inkster is currently closed to thru traffic.  A detour route has been posted.  This project is scheduled to be substantially completed and open to traffic in mid to late August.

Inkster Road Rehabilitation, Northwestern Highway to 13 Mile Road

Inkster Road between Northwestern Highway and 13 Mile Road is closed and a detour route has been posted that accommodates this project as well as the 13 Mile Road Project identified above.  Local access to residents on Inkster Road is being maintained from Northwestern Highway.  This project is scheduled to be substantially completed and open to traffic in mid to late August.

13 Mile Road Rehabilitation, Drake to Farmington

Currently, local access is being maintained in the eastbound direction only.  Westbound 13 Mile Road between Drake and Farmington is completely closed.  Access into the construction zone will be maintained only from Drake Road and all traffic will exit the construction zone via Farmington Road.  A detour route has been posted.  This project is scheduled to be substantially completed and open to traffic by September 1.

Drake Road Rehabilitation, Grand River to 11 Mile Road

This paving project is underway.  Drake Road will remain open during construction; however, it will be reduced to one lane with flag control during daytime hours as necessary.   

9 Mile Road and Halsted Road Intersection

This project includes the improvement and modernization of the traffic signals, as well as pavement reconstruction with the addition of right turn lanes on all approaches of the intersection.  The intersection is completely closed and all Halsted and 9 Mile traffic will be detoured around the project. This is scheduled to be open to traffic by September 1.

2018 Citywide Asphalt Replacement Program

Attached please find a map that identifies locations where asphalt pavement repair will be completed throughout the 2018 construction season.  Two-way traffic will generally be maintained during work at these locations by utilizing flag and traffic control as well as temporary lane and shoulder closures.  
2018 Asphalt Replacement Program

2018 Citywide Concrete Replacement Program

Attached please find a map that identifies locations where concrete pavement repair will be completed throughout the 2018 construction season.  Two-way traffic will generally be maintained during work at these locations by utilizing flag control as well as temporary lane and shoulder closures.  The repaired lanes will need to remain closed for up to a week to allow the new concrete to cure but it is expected that two way traffic will be maintained. 
2018 Concrete Replacement Program

2018 Citywide Sidewalk Replacement Program

Attached please find a map that identifies locations where sidewalk maintenance and repair will be completed throughout the 2018 construction season.  Two-way traffic will generally be maintained during work at these locations by utilizing flag control and shoulder closures to complete the work. 
2018 Citywide Sidewalk Replacement Program 

County Projects

Middlebelt Road, 10 Mile Road to 14 Mile Road (Consumers Energy)

According to the Road Commission for Oakland County and Consumers Energy, this gas line maintenance and replacement project is scheduled to continue into the fall.  Work will be completed with shoulder closures and lane closures under flag control for much of the project; however, a full closure of Middlebelt Road over I-696 will be required to complete the work.  This closure is expected to take place no earlier than June 15 (after school lets out for summer vacation) and to continue for approximately eight weeks. 

Middlebelt Road, I-696 to 13 Mile Road (Water Resources Commission)

There will be lane closures in place on Middlebelt Road on Tuesday, June 12 to complete work on the Middlebelt Transport and Storage Tunnel.  One lane of traffic will be maintained in each direction while work is being completed.

8 Mile Road Concrete Repair Project, East of Halsted Road to Farmington Road

This Wayne County concrete repair project is nearing completion.  According to Wayne County, this 1.2 mile stretch of road work is a continuation of the 2016 project that ran short on funds before all work was completed.  A significant amount of the repair work is concentrated on the shared center left turn lane.  Work is expected to take place under lane closures; however, one lane of traffic will be maintained in each direction. 
 
For information about Road Commission for Oakland County projects, visit the RCOC website at http://www.rcocweb.org, and then check press releases and/or the real time traffic map.

Michigan Department of Transportation (MDOT)

I-696 in Oakland County

This maintenance work includes concrete repair, joint repair, and flood mitigation efforts by the Michigan Department of Transportation.  Nightly lane closures will be required for overnight work from 9 p.m. to 5 a.m. Monday through Thursday.  There will also be 10 full closures of the freeway on weekends that will occur between 9 p.m. Friday and 5 a.m. Monday morning.  Detours will be posted during these closures.  Updates and closure dates will be forthcoming as they are made available by MDOT. 

Detailed closure locations and dates for all MDOT projects can be found by visiting www.michigan.gov/drive then clicking on Construction Search.